    We're trying to set up ProofHQ to proof draft webpages that are sitting behind a password protected wall. So far following the guidance from WF "https://support.workfront.com/hc/en-us/articles/115003926727-Creating-a-Static-Website-Proof-in-Workfront-Proof%20">here isn't working and the WF support t...

    Views

    670

    Likes

    0

    Replies

    14
  • 11/7/18
    I can't seem to send a new idea exchange post. Anybody else seeing this issue? Sometimes it sends a captcha and unless I am not choosing the correct information on the captcha (tried a few times), and after captcha goes away, it just doesn't send the post after verifying. Polly Co

    Views

    613

    Likes

    0

    Replies

    7
  • 11/7/18
    We have team members that like to use Task Reports to see the important information they need and group projects in a way they need to see them about that work they need to get done. Most of this information is not provided on the Home Beta view. So they leverage the Task Reports and would like to c...

    Views

    551

    Like

    1

    Replies

    8
  • 11/7/18
    My organization is struggling to get a full picture of user allocation in Workfront. We currently use the tool to understand allocation for marketing campaign work and PTO, but are unable to capture other "ghost time" areas such as trainings, meetings, or service projects. Any suggestions on how to ...

    Views

    389

    Likes

    0

    Replies

    6
  • 11/7/18
    I have a task (Design/Build/Test) in a project that says that it is waiting on another completed task (Concept). It says this on the Updates tab of the Design/Build/Test task. Concept task is at 100%, and so is Design/Build/Test task. So why is Design/Build/Test waiting on Concept? Any help would be...

    Views

    240

    Likes

    0

    Replies

    3
  • 11/6/18
    Hi all, My company is looking to take full advantage of Workfront's Resource Management functionality. We're looking to solve a few pain points, listed below. I'm looking for tips on how to tackle these or best practices for Resource Management. -How to get Planned Hours to align with project scopes...

    Views

    239

    Likes

    0

    Replies

    2
  • 11/6/18
    Hi All, Looking for a way to create a hot sheet type report that doesn't take task owner into consideration. When I create the report below, if the task assignee IS NOT the task owner, the report does not present that person. I want to be able to see all assignees task list for a specific period of ...

    Views

    248

    Likes

    0

    Replies

    2
  • 11/6/18
    Does anyone know a workaround to get the task and issue assignments into one combined column? Every time I use the text mode, it reverts the issue and task assignments back to two separate columns on my report The text mode did work for combining task and issue - Reference Number, Entry Date, Name &...

    Views

    759

    Likes

    0

    Replies

    11
  • 11/6/18
    How do I hide all the keylines from multiple comments in my 2D proof? I am unable to see which keyline corresponds to what comment as every single keyline is showing all the time. In legacy viewer it only showed the comment that was open. Now that Legacy viewer is being phased out I would like to kn...

    Views

    337

    Likes

    0

    Replies

    2
  • 11/6/18
    I have got test box integration work as per needs in my workfront account. Is there a way to reset box integration so that i can connect another box account? so far i haven't found any literature or controls in settings to reset it. #product engineering team, can you add some control to reset box in...

    Views

    401

    Likes

    0

    Replies

    2