Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 3/2/20
    hi Stephen, one of the ways to access these is through a note report. I think this thread covers the basics. "https://one.workfront.com/s/question/0D50z00006Px3iKCAR/" https://one.workfront.com/s/question/0D50z00006Px3iKCAR/ -skye

    Views

    175

    Likes

    0

    Replies

    0
  • 3/2/20
    Has anyone figured a workaround for simplifying the amount of math a PM has to do to figure out the number of planned hours they need to assign to a resource (or multiple!) when a task spans a duration of multiple weeks? Our team is used to working in percentages by the week so it's been difficult t...

    Views

    357

    Likes

    2

    Replies

    3
  • 3/2/20
    Hi all, I'm the very new System Admin for my team. One user has the Planner level of access, and he was able to create a new project. However when he's in the Edit Project settings and he scrolls down to the Portfolio drop down, he only sees two very old portfolios to choose from. He doesn't see the...

    Views

    290

    Likes

    0

    Replies

    2
  • 3/2/20
    Hi all, This might be a dumb question, but I'm having trouble figuring this out on my own. How do you tag / notify everyone on a project in an update? Normally I'd search for a person or team by typing @ followed by their name, or I'd type the user or team name in the "Notify" field. Is there someth...

    Views

    385

    Likes

    0

    Replies

    3
  • 3/2/20
    Hello - Does anyone have an idea if it would be possible to do the following based on this screenshot: Using the | Master Creative Project Number to combine all 5 projects into a single line to see the minimum and maximum start date? So for the total length of time for Creative project 3929201...

    Views

    216

    Likes

    0

    Replies

    1
  • 3/2/20
    My final goal is to have a report showing column of "all note text from this week under each task" and filter the showing tasks for some assigned user. Filter is working good, but column is not working as I wanted. Assignment Users First Name Equal Jason and Assignment Users Last Name Equal Teng ...

    Views

    374

    Like

    1

    Replies

    2
  • 3/2/20
    I don't see where it is possible to edit a project in the mobile app. Any ideas? Michelle Bowden Fiserv ETG

    Views

    323

    Likes

    0

    Replies

    2
  • 3/2/20
    Hello - We are currently implementing Workfront and trying to determine the best way to track what "phase" of the lifecycle each project is in (Initiating, Planning, Executing, Closing, Complete). Does it make sense to build each one out as "Statuses" that equate back to "Current"? For example - cre...

    Views

    411

    Likes

    0

    Replies

    3
  • 3/2/20
    Is it possible for co approvers to receive notification when someone else has approved an issue/request approval so they wont bother to go in and approve. Doesn't appear to be such a notification, but maybe there is another way to achieve?

    Views

    188

    Likes

    0

    Replies

    0
  • 3/2/20
    Hi Everyone, We are looking for system admins in Marketing to take a short survey on Jumpstarts (i.e., out-of-the-box configurations in your Workfront instance). Please complete the following survey if you would like to give feedback! http://survey.qualtrics.com/jfe/form/SV_dcERkphmdevW0Ch Thank...

    Views

    280

    Likes

    0

    Replies

    2