Hi folks, Does anyone know how to use text mode and put a filter on the Date Range field? The Date Range field is a text mode field available in WF's off the shelf report 'All Open Timesheets'. I'd like to create a copy of this report and put a filter on it to only show data based on a Date Range ...
I have a task report that has some calculated columns. Has anyone figured out a work around to summarize a calculated column that has a value expression? On my report I'm also trying to get a column with the predecessor task's actual completion date (or better yet the custom field "Actual Audit Date...
Hello All,Just digging into some NWE stuff and noticed that my links to specific tabs no longer works. I set them up based on this article: https://one.workfront.com/s/article/Linking-Tabs-from-Lists-and-Reports-1370315261?language=en_USThe URL comes up correct, but it doesn't go to the specific das...
Is there any way we can allow Commit Dates to be edited in-line in task reports? It would be VERY helpful for our users to be able to edit Commit Dates directly from a report. Some of our users have 100+ active tasks so using the Home screen or My Work screen isn't very helpful because we need to sh...
I have this question in to our rep: We are working with another company who needs access to mark-up proofs in Workfront proof. We are currently creating a public link but it causes delays and proof ownership issues. They are also WF customers --- is there a way to provide an existing WF customer acc...
So, I learned this from LEAP last year and it works great. you can see what task a Project is on without clicking into project then task list etc. ***But - we have a case where we have 2 templates being used on 1 project. 1 of them does NOT use predecessors ...hence, we get the current task from one...
Hello, I am creating an issue report with a column that should show the resolving project's name, if the issue has a resolving project. Otherwise, the issue name should display. This formula seems to work, but strips out the hyperlink to the issue/resolving project: displayname=Project or Issue Name...
Hello, I am creating an issue report with a column that should show resolving project's status name. If that does not exist, the issue's status should display instead. I got this to work, but the results show the status key (EX: CUR, CAN) instead of the actual status name that we associate with thes...
Hello, Does anyone know if it's possible to force sort the results of a valueexpression in a report? For example, I'm creating an issue report with a column that shows the resolving project's Last Update Date. If the issue does not have a resolving project, then the issue's Last Update Date will dis...