Expand my Community achievements bar.

Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 6/26/25
    I am trying to use Baselines - but I am not seeing how I would show that a project has slipped a month from its start.  Does anyone have a process they are using to calculate slippage in a project or a series of projects?  Thanks in advance for any guidance you can provide! Sue

    Views

    299

    Likes

    0

    Replies

    2
  • 6/26/25
    I created an hours report that breaks down hours by hour type in separate columns. Is it possible to sum each column? I tried the following but it gives me a sum of all the hours, not just the "X40" hours I'm filtering for. aggregator.displayformat=doubleAsIntaggregator.function=SUMaggregator.nameke...

    Views

    479

    Likes

    0

    Replies

    4
  • 6/25/25
    Hi all, I need to create a filter for a task report to show all tasks with planned hours = 0. However, (task) planned hours does not seem to be available field for filtering the task report. Is there some workaround for this? Thanks!

    Views

    342

    Likes

    0

    Replies

    2
  • 6/25/25
    We have a custom form that feeds a report for our stakeholders to know the status of the project. The % complete is not a clear indicator of the phase of our work/the project. Right now updating the status field in the form is manual and not tied to anything. We want to select specific tasks (mile m...

    Views

    303

    Likes

    0

    Replies

    2
  • 6/25/25
    My group's tasks (task groups) shift as the project is being worked on. We apply one long template that includes all possible tasks and then delete groups of tasks as we realize the work is not necessary to complete or not required of the project. We've tried to be very organized with the groups of ...

    Views

    247

    Likes

    0

    Replies

    1
  • 6/25/25
    I have an Assignment Report showing Tasks assigned to users with a specific job role. I am unable to edit the report in-line which I saw a post relating to adding this text mode to make it editable but it's not working: isInlineEditable=true Anyone know how to get an assignment report to be editable...

    Views

    422

    Likes

    0

    Replies

    4
  • 6/25/25
    is there any way to limit the character count in a custom field? Trying to make a character limit of 200 characters.

    Views

    264

    Likes

    0

    Replies

    1
  • 6/24/25
    I'm trying to pull the text from descriptive text fields into a calculated field that starts with an if statement, but I can't get the text to show I can only get it if its a text field. Any suggestions on pulling descriptive text from those fields ? Below is the if statement I started with. IF({DE:...

    Views

    295

    Likes

    0

    Replies

    1
  • 6/24/25
    I am using this calculation on a date field to calculate due dates. ADDWEEKDAYS($$TODAY,4) How can I modify this to exclude holidays so that they are not counted as business days in the calculation? My instance of Workfront does not have a holiday library so I would need to list them manually in the...

    Views

    528

    Likes

    0

    Replies

    6
  • 6/24/25
    Hi all, We moved to managing users via the Admin console recently and one area we're unclear about is deactivating users. As a Product Administrator, I'm happy with removing users from the production environment by deleting their product in the console. But should I also need to deactivate the user ...

    Views

    269

    Likes

    0

    Replies

    2