Recurring Task Help | Community
Skip to main content
Level 2
October 4, 2024
Question

Recurring Task Help

  • October 4, 2024
  • 1 reply
  • 1422 views

Hello! I am a fairly new Workfront System Admin (7 weeks in now) and having some trouble setting up recurring tasks, so hoping someone can help.

 

A few different users within my organisation are having issues with recurring tasks, and there doesn't seem to be any logical reason as to why - even when seemingly copying the set up of a recurring task that has previously worked within the same project, we're seeing issues.

 

The issues seem to differ based on the task constraint;

  • When selecting either 'As late as possible', 'As soon as possible', 'Must start on', or 'Must finish on', even when setting the start time of the task on the task to 09:00, when the task is created it seems to put the planned start time as 16:00. This then pushes the task over 2 working days (the task is 1hour, and shows in workload balancer as 1hour on the first day, then 0 hours on the second day). I can't seem to figure out why the time is changing?
  • When selecting 'Fixed Dates', the task appears to set up correctly, but then doesn't appear in the Workload Balancer on the project. Even if assigning users to this particular task that are new to the project, their names appear on the Workload Balancer, but the project doesn't appear under them, and so neither do the tasks.

Does anyone have any ideas as to what's happening or why? I'm sure (hopeful) it's something simple I'm missing!

 

Thank you, Lana

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Sven-iX
Community Advisor
Community Advisor
October 4, 2024

Hi @lanala 

Welcome 🙂 
Can you post a screenshot of the recurring tasks in question that show constraint, predecessors, start/end times with hours?

LanaLaAuthor
Level 2
October 4, 2024

Hi, hope the attached helps. It's s test project I've set up to test various ways of setting up recurring tasks.

 

Thank you, Lana

 

 

 

Sven-iX
Community Advisor
Community Advisor
October 4, 2024

Thanks @lanala 

So the recurring tasks don't really have predecessors. Must Start On should be just fine. 

When you replicate a task, do you right-click and select "duplicate"?

 

Let's try this for the 121 tasks

  • Check to make sure the project schedule is in the correct timezone (ie YOUR time zone)
  • Set child tasks to "Must start on", and to the same date & time (9am)
  • Set the child tasks 2,3,4 to the correct planned start date

Once they have the correct start dates and all show 9am, you should be able to right-click, select "duplicate". This will add copies of the selected tasks, and you can then rename them and set their start dates. 

 

Let me know what it looks like?