Expand my Community achievements bar.

Wondering how Workfront Proof works? Join our AMA on May 8th and ask our Community experts!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 9/11/23
    Hi everyone, I need some help. Is there a way to remove a prefix from a currency when a report is exported to excel.Workfront was able to show me how to remove the prefix in Workfront, but when I export to excel, it still shows up.Any ideas? Thank youAmina O.

    Views

    598

    Likes

    0

    Replies

    4
  • 9/11/23
    Is there a way to stop a Request due date from automatically populating to align with the Project Planned Completion date? I've only seen this happen to Requests assigned to an Iteration (and the iteration is not schedule to be complete on the same date as the Project). Thank you in advance!

    Views

    274

    Likes

    0

    Replies

    1
  • 9/11/23
    Does anyone know if we are able to update existing reports that are currently using Legacy Filters to the new standard report filters without having to manually delete a report and re-create it?  

    Views

    586

    Likes

    0

    Replies

    2
  • 9/11/23
    We have a calculated field that generates a name based on project parameters. I'd like to save that calculation into a text field that doesn't change even if the parameters of the project change down the road. Is that possible?

    Views

    417

    Likes

    0

    Replies

    2
  • 9/11/23
    Hi all, I have a report, which shows Planned hours, Actual Hours and Planned Revenue for completed projects. But I also need to be able to show the Task Assignments (by Job Role). I'm sure that this is possible, but I'm not finding the right starting point to get the fields I need. Thanks in advance...

    Views

    755

    Likes

    0

    Replies

    6
  • 9/11/23
    Someone asked this question years ago but didn't receive a solution. I'm bringing it back to the top. We repeatedly build marketing portfolios for our event offerings. All are similar as far as the projects within them are concerned. Is there an easy way to duplicate an entire portfolio for each yea...

    Views

    574

    Likes

    0

    Replies

    3
  • 9/11/23
    I have a Task Report that has a Text Mode Grouping that groups the Tasks into weeks (Mon-Sun) based on the Travel In date . The problem is when the Travel In date is a Sunday, the Task is grouped into the subsequent week instead of the week (Mon-Sun) it's in.Is there a way to update this text mode t...

    Views

    413

    Likes

    0

    Replies

    2
  • 9/11/23
    Why does after you assign different requests to different people, they pull through on the project under 'people'? 1. I thought the 'people' under the project are the people part of the team assigned to this project?2. If I remove those names, does that un-assign them on the requests?3. Does this al...

    Views

    1.1K

    Likes

    0

    Replies

    6
  • 9/11/23
    REF# 11642560. I received approval from legal (9/7) but did not receive the final 'Approved' email nor can I locate it on Workfront. This document was also originally assigned to Bert. Any assistance is greatly appreciated. 

    Views

    358

    Likes

    0

    Replies

    1
  • 9/11/23
    Is there any reason why the math's from a custom form doesn't add up? It should be as per the highlighted yellow: Business value score (100) PLUS Time Criticality Rating (20) = should give the total rating of 120 but it's pulling through as 20?  

    Views

    624

    Likes

    0

    Replies

    6