Update: This thread is resolved. There was a glitch in the backend that was not allowing the setting to work. Now it is fixed. Solution: In the access level assigned to the user, select the feature : "Never give access to the whole project when assigned to a task or issue". Unless the project is di...
I am not seeing opportunities to integrate Workfront in any way with Litmus email build/proof software. That said, has anyone used both programs for proofing within their organization and find ways to maintain the workflows/approvals in Proof while integrating/sharing dynamic links to email proofs i...
I accidentally switched back to the current home experience and want to go back to the new home experience released earlier this year. I can't seem to find a way to do this. Any help would be much appreciated!
I have a user who's set up as a Planner on Workfront. As a result, they have manage rights to proofs. However, when they go into the Proofs page, they only see two proofs from the dashboard, or the folders. But they can go to any project that they are allowed to see and view any and all proofs assoc...
Hi, I can't seem to find a status which will change a current project to remove the resources form workload balancer while the project is re-planned. Does any one have any ideas to help me?
Hello, I am doing Task Discovery for Jira / Workfront Connections. There i want to check for the possibility of:1.Updating a project status from Workfront to JIRA 2. Is there a way via Workfront to see if a task has been assigned to a Sprint in Jira.Eg: i have created one story in Workfront. That st...
Hi, I am looking to add a column rule for a report to highlight in red if the actual completion date exceeds the planned completion date. I tried to find other conversations on here but couldn't find an exact solution.
Within our Issue Task there are a bunch of System Captured Fields that show up in the "Issue Details" tab which we have no use for. We've been told that these System Captured Fields cannot be hidden. If that is true, is there an alternate way to make it so they don't display. No one uses these at al...
How to change the status of a task based on the status of the predecessor task ?See atteched file. Is there a way to have a task status controlled by the status of it's predecessor? Specifically what I am looking at doing is when a task status is marked complete the task that is dependent upon it co...
Hi Community, Our team is trying to build a report where we want to be able to group the number of assigned tasks and the associated planned hours but then filtered by a specific time frame. We would like to be able to have it summed up and preferably in a chart. We would also need to filter by rol...