Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 2/27/24
    Looking for a way to view Net available hours by user on a report level.  The system calculates in the planner view when viewed by project but not is the user view. Our support team/Adobe says is it is not possible to leverage this calculation in a report.  This is a basic calulation when understand...

    Views

    168

    Likes

    0

    Replies

    1
  • 2/27/24
    Hi- Is there a way to summarize a column in report with sum and average both? Average value at sub-grouping (child) level and then sum of all sub-grouping level at group (parent) level. Basically, average of all the numbers which are under subgroup and then sum of all the subgroup numbers which are ...

    Views

    245

    Likes

    0

    Replies

    1
  • 2/26/24
    I am having some challenge with rounding the Portfolio On Time number to two decimal places. I followed the instructions from the resources I found on the Workfront community and Experience League but with no success. I have tried replacing the valuefield with valueexpression but no value display. N...

    Views

    298

    Likes

    0

    Replies

    2
  • 2/26/24
    Hello, all our users of workfront received a 'Welcome to Workfront' e-mail from Adobe on Sunday 2/25. These are users that have had accounts for years. Was there a mass e-mail sent by mistake or is this some kind of scam?

    Views

    245

    Likes

    0

    Replies

    1
  • 2/26/24
    Hi, I'm trying to build a project report that can pull information stored in custom forms in both the projects and issues. Despite all my research, I didn't find any workaround. 

    Views

    275

    Likes

    0

    Replies

    3
  • 2/26/24
    A team in our instance work from a Request Queue where Issues are assigned out. They track this work with Issue Reports filtered with 'Assigned To: Name'.A recurring problem is that when multiple users are assigned to the same Issue a Primary Assignee is selected. The Issue will then only show up on...

    Views

    1.2K

    Likes

    0

    Replies

    17
  • 2/26/24
    While logging into Workfront, I'm encountering the error message "No account associated with the email address." However, this account still has planner access in Workfront, as I've confirmed while using the administrator account.

    Views

    226

    Likes

    0

    Replies

    1
  • 2/26/24
    How to give proof HQ dashbaord access to planner user ? 

    Views

    162

    Likes

    0

    Replies

    1
  • 2/24/24
    Hello, I cannot change the duration of a task - keeps reverting back to 1 day.  Do I need to modify task contraints?

    Views

    552

    Likes

    0

    Replies

    6
  • 2/23/24
    We're interested in best practices for extending project time/end dates, when the project deadline has delays and time extension has been approved. We mostly create templates for projects with Calculated Assignment tasks with As Soon As Possible task constraints, using predecessors. Occasionally we ...

    Views

    609

    Likes

    0

    Replies

    2