I've got it working! It's more on how my project owners are scaling out tasks and how I was comparing template duration vs planned duration vs actual duration. Learned that we're all over the board! HAA!
I've also noticed, that the "actual duration" field under the Working time section, is tracking logged hours and my team is very bad at logging hours. So I need to work with what is under the section project dates
@KellieGardner Thank you for reaching out. It is not working. I get empty fields. I'm assuming it's because we currently are not logging our hours/time for each task; therefore I'm looking for something that will show the duration between the actual start date (the day the job's status is switche...
Hello! I'm trying to create a project report that shows actual duration of projects. One column is pulling the template duration, but I also want to show in a separate column the duration the project ACTUALLY took. Taking the actual start date and add up the actual completion date and show what tha...
Hi @Lyndsy-Denk - that did the trick! I started with that field but changed all instances of ID to :name. Which is where I then started confusing myself. I've taken a few webinars on API explorer with Workfront but I'm not fully confident with it yet. I appreciate your help though and it solved m...
I am trying to get a portfolio column to show up in a task report. What am I doing wrong? I don't want to group by portfolio; just a column showing the portfolio associated with the project and task.displayname=Product Segmentlinkedname=lastConditionNotenamekey=view.relatedcolumnnamekeyargkey.0=last...
Prior to 4/11/24: I have a few custom fields on a custom report attached to each of our templates/projects where any user can add notes to (the field is for additional and ongoing comments that is separate from the Updates section) with a contributor access. With the Release made on 4/11/24, that fi...
@richard_carlson Thank you for reaching out and responding. I have a custom form attached to all our templates where we can indicate the marketing and product line experts that will also have to review and approve all advertising assets created. Someone on my team wanted the proofing workflow to pu...
Is there a way to pull in users from a custom form created field in a Workfront project to a proofing workflow in the proofing tool? Or do all users in a proofing workflow have to be manually added when creating the workflow?