Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 10/25/18
    Hi Reporting gurus, I may be overthinking this one. Is there a way to get a calculation on 'Template duration' to my calculated column of (entry date to requested due date)? (Thank you for your TEXT MODE PDF @Narayan Raum ) I'm basically looking for the day difference from (Entry date to Requested d...

    Views

    267

    Likes

    0

    Replies

    4
  • 10/25/18
    Hello! I would like to track my initial baseline dates, then my negotiated rebaselined dates, and also my actuals. I am using planned start date and planed completion date for the original baseline and actual start date and actual completion date but is there any field I can use for a manually enter...

    Views

    321

    Likes

    0

    Replies

    5
  • 10/25/18
    Hi All, Is it possible to get a task to start as soon as the predecessor is complete? For example, if Task #1 was supposed to take 2 weeks, but I finished it today and completed it, can I get the planned start for Task #2 changed to today? I have an issue where tasks could be started sooner, but th...

    Views

    171

    Likes

    0

    Replies

    1
  • 10/25/18
    My creative team are placing "issues" on certain projects and assigning to clients for their input. My clients aren't getting notifications in WF or in email form. Is their a certain permission that the clients need? Brian Daly Independence Blue Cross

    Views

    337

    Likes

    0

    Replies

    4
  • 10/25/18
    We use a pool of freelance creative resources. Some bill at an hourly rate and others on a by-asset rate. We've set an hourly rate within the accounts of our hourly freelancers and can track their cost as they log time on tasks. This approach doesn't provide an accurate picture of costs for tasks as...

    Views

    219

    Likes

    0

    Replies

    2
  • 10/24/18
    Hello! We do a good amount of customs reports in the system and I'm attempting to minimize the different system we utilize. I want to produce status reports from the system and can input the data various ways either custom forms, update sections, etc. That said, I'm wondering if anyone has had succe...

    Views

    233

    Likes

    0

    Replies

    2
  • 10/24/18
    Is it possible to apply column rules to calculated column in a report? I have calculated variance between planned and actual hours @ task level and want to make any results less than 0 present with green text and results greater than 0 display red text. Steve Teitelbaum Federal National Mortgage Ass...

    Views

    194

    Likes

    0

    Replies

    2
  • 10/24/18
    I have been playing around with the resource planner and am really excited about the updates. I was worried because the one live now does not do everything we need. But in the preview it is awesome. I have a few questions though and wanted to see if any one knew about them. Resource Planner - Will...

    Views

    205

    Likes

    0

    Replies

    2
  • 10/24/18
    Is there an easy way to build a report that shows me a number of projects by portfolio and program? Thanks, Jason Jones Analyst, Digital Application Management Lincoln Financial Group

    Views

    180

    Likes

    0

    Replies

    1
  • 10/24/18
    Hello! I'm looking for use cases for what can be done when integrating SharePoint and Workfront using Fusion. We have looked at the out-of-the-box integration and my understanding it is only allows pushing documents back and forth between the two applications and we are looking for a more robust con...

    Views

    352

    Likes

    0

    Replies

    3