Hi, Does anyone know if it is possible to capture the time period between specific status changes on a task?
In the screenshot I would like the time period from the status change 'Branch Amend' to 'Proof at Branch'.
For each projects task the last status will always be Proof at Branch, however the first status could be one of three: Branch Amend, Branch Amend Minor or Amend to Print. My overall aim is to create a report that shows me how long our design team take to do each amend. At the moment I have no way of knowing this unless I go into each project individually and manually work it out. And since we process up to 100 projects a day this just isn't an option. Does anyone have any suggestions?