Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 3/21/17
    How do I delete a Workfront request?

    Views

    1.5K

    Likes

    0

    Replies

    3
  • 3/20/17
    Hello, I'm running in to an issue where we can't in-line edit the cells in our project report. The custom field that we are trying to edit is in the project custom form - and I know that WorkFront only allows in-line editing on the main object. So if it is a Task report, you can only in-line edit ...

    Views

    469

    Like

    1

    Replies

    3
  • I'd hoped to write this one up as a blog, but Earth simply spins too quickly, so instead, I'd like to invite you to try out this textmode gem I invented this week. In fact, let's at least make a game of it! WARNING: If you're going to play, WAIT to read the other threads below, and SPOILER ALERT: th...

    Views

    926

    Likes

    0

    Replies

    16
  • 3/16/17
    What is the best practice to set up time as a System admin for logging out of Workfront inactivity?

    Views

    631

    Likes

    0

    Replies

    3
  • 3/15/17
    Hi there, Just wonder if anyone else got the same issue. It keeps occurring that tasks disappears from users Timesheets. Tasks are still in progress, not completed, not passed Due Date, haven't been marked as 'Done', user still assigned to it, etc. For some reason all of the sudden they disappear ...

    Views

    1.2K

    Likes

    0

    Replies

    15
  • 3/14/17
    I've tried to find via Workfront a good explanation of how this works and examples of reporting. Any PM's out there able to provide greater insight? Examples? Thank you!

    Views

    792

    Likes

    0

    Replies

    6
  • 3/9/17
    I'm wondering if there are any best practices for projects that have closed. Is there a suggested archiving system or do portfolios/programs continue to house ALL projects both active and completed. Our portfolios are created based by business area.

    Views

    520

    Likes

    0

    Replies

    2
  • 3/8/17
    Hello, Does anyone know if there's a way to build a report/column that shows how many days beyond the planned completion date a project is? So for example, if a project was due on March 6 and it is now March 8 is it possible to have a column that shows that the project is 2 days late?

    Views

    555

    Likes

    0

    Replies

    7
  • 3/8/17
    Hi Everyone, I am currently using this expression to calculate the # of days between two dates: DATEDIFF(Entry Day,Actual Completion Date) I'd like it to ONLY count week days. Is there any way to filter out the weekend? Note: Entry Day is a custom date field: IF(ISBLANK(Entry Day),"",Entry D...

    Views

    1.1K

    Likes

    0

    Replies

    8
  • 2/27/17
    Hello ~ I have a report that shows Users and licenses allocated (Plan/Work). However, not all the licenses are being used. For instance, I have 47 work licenses but only 36 are currently allocated. Is there a text or code to show the remaining 'open' licenses? Thank you

    Views

    884

    Likes

    0

    Replies

    15