All, I am working with a client where most of the Marketing Department is using Workfront except one team that is more enamored with Asana than Workfront. The team lead is a certified Scrum Master and is trying to move their very analog method of working in an Agile fashion over to a digital platfor...
I've done a search to try to find what I'm looking for and having difficulty seeing a previous post on this topic. I have a Request report that is pulling in the request name and the resolve project name, and I've combined those columns. The resulting column displays the Request:Resolve Project, and...
Reminder : Starting Tomorrow, May 15, 2019 To streamline the Workfront brand, we are phasing out all legacy AtTask domains and updating Workfront URLs. Going forward, all Workfront instances will use only the .my.workfront.com domain. This update will be in three phases. The first phase will start o...
So I have a task to do something in the office based on a future onsite tasks planned start date. So the due date for the in office work is valid and uses the future tasks planned start date minus x days to create the in office tasks due date. There is some information in the future onsite task that...
Someone at LEAP mentioned the notion of this. We can use the published queues to route to an unpublished queue. At first I was thinking this meant this would give us addtl drop downs at the request level, but that is not accurate. I was wondering if any of you utilize this process and what the use c...
Hi Everyone - So, I am presenting to Leadership asking for buy-in for more team members to help me with WF. As of right now, I am a one man show - I customize dashboards, templates, layouts, build reports, quality control, troubleshooting, resourcing, etc. You name it, that's me! Any insight would b...
I'm trying to use a kickstarter to add tasks to an existing project. I'm able to add my tasks... 1 parent task and a bunch of sub-tasks. They all come in fine. But I'm struggling with Duration and Hours. I want a 3-day duration and 4 planned hours for all tasks (except the parent task). I've tried b...
Hello - wish I could have asked this last week but it's new ! I have a custom form that is used for events that require mascots to show up at different times. so I have 4 date/time fields that are required.an external viewer reviews the custom form and has no access to make any edits. review and sen...
All, I'm trying to add color to entries in columns since it was one advanced tip I learned at Leap this year. I'm having some trouble with the actual hours column in the attached image. I'm not able to replicate the color in that column like I did for the actual completion date column on the far rig...
I'm wondering, why can't I add a Group to a Project template? I'm hoping I'm missing something but seems it's not a field I can select when setting up templates. Our projects are applied to different groups and subgroups, it seems weird to have to manually add that when creating the project from a t...