Expand my Community achievements bar.

Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 2/28/20
    My Portfolio Optimizer is missing for all Portfolios... Any idea what I could have done?? Even tried new ones and nothing shows? Jordan Martinson LeaseTeam, Inc.

    Views

    745

    Likes

    0

    Replies

    10
  • 2/28/20
    Hi there! I've defaulted to the Workfront admin/trainer for new hires within our MarComm team and I'm interested in learning from others in similar roles. I'm especially eager for resources or training docs you've found helpful as you educate new hires in your organization's instance. The trap I fin...

    Views

    274

    Likes

    0

    Replies

    3
  • 2/28/20
    I've got a template set up where I have several tasks assigned to a Designer, Brand Manager, or Copywriter. Is there a way when setting up the template to easily replace all of the Role placeholders with a specific user? I've seen this before on Workamajig, but I can't figure it out on Workfront. Se...

    Views

    540

    Likes

    0

    Replies

    12
  • 2/28/20
    When one of our team members submits a request, we want them to select a start date or due date and show calculated dates for hand offs and approvals. Then we can use conditional logic to warn about time constraints or whatever. Unfortunately, it doesn't seem like calculate fields will actually calc...

    Views

    550

    Likes

    0

    Replies

    8
  • 2/28/20
    2020 is a Leap year - and it is almost leap day. It's so nice to have an extra day this year to get stuff done... and it's got me thinking, what would I do with an extra day EVERY month? For me, I would have to use at least a few of my extra days for some self care, something like a nice long massag...

    Views

    100

    Likes

    0

    Replies

    0
  • 2/28/20
    Change is difficult but necessary. I'm a user. My group is my family. We have a portfolio with programs and many projects. We are each a project because everything is a project. We're on others' projects. We have issues, plural. We have tasks, too many to count. Our issues are resolved by projects, ...

    Views

    147

    Likes

    0

    Replies

    0
  • 2/28/20
    Hello All, I have an issue report and I am trying to reference the planned completion date of a specific task in one of the resolving projects. I'm not even sure this is possible, but hoping it is. I'm using iterate with an If statement. Any ideas? displayname=Active Project Phase(s) listdelimiter= ...

    Views

    206

    Likes

    0

    Replies

    2
  • 2/28/20
    Hi Karen, Well, for a first post, you picked a doozy! Since the granularity you seek (number of document rejections) is not preserved natively within Workfront, I believe you'll have to construct your own datasource (on a going forward basis) using special type of calculated custom data I call "http...

    Views

    169

    Likes

    0

    Replies

    1
  • 2/28/20
    Hi! I am trying to understand how should the work flow be - Currently, we have setup as follows: - 1st review holds approval/ reject when it's "completed". However, when it's rejected, it moves back to "in progress". changes required by sponsor will be input here in comments - when changes ar...

    Views

    493

    Likes

    0

    Replies

    6
  • 2/27/20
    Currently the partners we work with have access to the documents tab so they can review items and add when needed (they are designated int eh field project owners and that probably can't change). We're experiencing an issue where they are previewing designs that were not shared (or ready to be share...

    Views

    311

    Likes

    0

    Replies

    4