Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.
“Assign Design” is often the first task on a project. We would like to set the default end date of all Assign Design tasks to a day of the week (Tuesday). Is it possible to add a lag type to the first task of a project, utilizing “3w” somehow? We would prefer to achieve this without having to add a ...
We are having trouble getting users to convert issues into tasks then assign the task to a different destination project rather than keeping the task in the request queue project. The ideal process would have them converting the issue/request into a task and then choosing what project to have the ...
Me again! I have a project report with a task collection column; however, I need to add an if statement so that I'm only showing tasks with a specific template task ID. I'm not the strongest at writing IF statements so I'm hoping someone can help me out, here's what I have: valueexpression=IF({templ...
Hi all, I have a scenario that copies a value from a Job Number field to the project name as a prefix. Occasionally someone will create and then immediately delete a project which causes several of my scenarios to throw an error. Your scenario PROJ-Add Job Number to Project Name v2.0 | Productio...
Hi All, I've created a Task report, and I'm trying to calculate actual durations for tasks in this year's projects (in order to update our templates for next year). It's been determined that the Actual Duration field is of limited value because in many cases, users marked tasks complete without f...
Where can I find the previous Webinars in Workfront before migrating to experience league we can easily navigate those session via event but now really confusing with this layout.
Hi, Wondering if there is an answer / solution for this: When setting a Start Date for a Task and setting it to a date (i.e., Sep 9) - is there a way to set the the Due Date to the same Date (i.e., Sep 9), without using 0 Days as the Task Duration? We had a template setup that was working this way...
I am once again coming to all of you to help me with the text mode for my task collection. I have a Project report and can successfully pull the task collection to show the name and planned completion date but whenever I attempt to also add the parent name I get an error. The closest I came is paren...
When I open this app, I get a message to go to my settings to add the supported links if I want to continue my work on Adobe Workfront Mobile application. Anyone know what this is? I don't see anything in my settings related to adding supported links...Thank you!