  • 9/12/17
    hi folks, I have a user who is experiencing long lag times when going to the custom form tab of a project. Google Chrome, planner license. This also happened to a different user 2 months ago. We were unable to get traction via helpdesk--Workfront was not experiencing network issues, and deleting cac...

    Views

    278

    Likes

    0

    Replies

    3
  • 9/12/17
    Hi all, I'm seeking wisdom on how to create a calendar of selected tasks (i.e. send to publication, ship booth, etc.) by program/project. I'd like to share this calendar with all Workfront users to keep people aware of firm deadlines. Has anybody been able to create this type of task calendar? Thank...

    Views

    354

    Likes

    0

    Replies

    4
  • 9/12/17
    Sorry for the catch-all post -- but I've been looking at "https://support.workfront.com/hc/en-us/articles/216632048">this support page on EAC as I'm trying to understand the ramifications of the two options available for "Performance Index Method ('Hour-Based' or 'Cost-Based') and "Estimate at Compl...

    Views

    216

    Likes

    0

    Replies

    2
  • 9/12/17
    Does anyone know if it's possible to work across two different Workfront instances? We're a marketing agency and run all of our projects through Workfront, and give all of our clients have review licenses. One of our clients has now also implemented Workfront and I'm not clear on if/how the two inst...

    Views

    413

    Like

    1

    Replies

    4
  • 9/12/17
    Anyone has got idea how to create a report which I could attached to a project as a dashboard and would show me open timesheets for Project Team. Ideally i would like to be able to see if anyone from my project team is behind with putting hours and submitting timesheets. Anyone? :) Dagmara Garwell B...

    Views

    425

    Likes

    0

    Replies

    8
  • 9/11/17
    We set the UAT Fixes task to match the planned completion date of the UAT using a FF (finish-to-finish) option to ensure the resource is available to complete this by the time UAT is planned to be done. In this example, UAT is planned (scheduled) to be completed 9/19 and therefore we expect the reso...

    Views

    157

    Likes

    0

    Replies

    1
  • 9/11/17
    Hi all, I've add a custom form to our programs. Because we use programs to denote an event for which we have many deliverables. It doesn't appear that I can add program information on the calendar. What I was trying to do was pull the event date custom field data from the custom form that sits at th...

    Views

    177

    Like

    1

    Replies

    1
  • 9/9/17
    Another Workfront Product Manager here! I am responsible for the project management (e.g., Projects, Tasks, and Issues) area of the product. I would love to spend time on a 30 minute call to learn more about how you use the Workfront to manage projects and workflows/processes in general, what you us...

    Views

    420

    Likes

    0

    Replies

    10
  • 9/8/17
    I am building a report and I need to pull in all teams that the person is on. What do I add to pull in all of the other teams the person may be on? Thank you, Becky Grosh Humana

    Views

    216

    Likes

    0

    Replies

    2
  • 9/8/17
    Hello All - I am looking to create a report and am having some trouble. Most of our work comes in as a Request a Request Queue - so its an Issue of a Project. The issues are then converted to their own projects by someone on our project management team. When this is done, the Project Owner and Enter...

    Views

    437

    Likes

    0

    Replies

    5