  • 4/19/18
    I have a report where the prompt filter is by actual completion date - the user wants to track some details to projects that are completed, cancelled, dead within a certain time period. The problem we realized is that cancelled and dead projects do not actually have an actual completion date, logica...

    Views

    503

    Likes

    0

    Replies

    8
  • 4/19/18
    Hi there, I'm havung some annoying issue with one of my reports and i have no clie what's wrong with it! When running the report itself - it looks so nice and tidy. But as soon as I run it in dashboard it gets some empty spaces in columns and makes the report looks huge... Any ideas why? And how cou...

    Views

    181

    Likes

    0

    Replies

    2
  • 4/18/18
    Hello Everyone, Is there a way to prevent people from backdating hours (i.e. logging hours in a task/issue/project for 2 months ago)? I know we can prevent logging hours on completed tasks/issues. But what if it's still open, or I suppose they can still open it, log time, and close it again. Hope yo...

    Views

    789

    Likes

    0

    Replies

    12
  • 4/18/18
    Hello - I am looking for tips on the best approach to manage hours allocations by month. By default, Workfront will evenly allocate, or "peanut butter spread" as I like to say, the total planned hours from the planned start to the planned completion date. On our larger projects, this is not really h...

    Views

    207

    Likes

    0

    Replies

    1
  • 4/18/18
    Hey community! I was wondering if anyone could help explain why a Start-Start dependency on a task results in Can Start = False if the preceding task status is not logged as In Progress? Until today, we were sometimes using the Start-Start dependency as a way for tasks assigned to different people t...

    Views

    129

    Likes

    0

    Replies

    0
  • 4/18/18
    I'm trying to create a report that shows the actual hours worked vs the original baseline hours. What I have is a Program with Projects that are all a month long and are set up for the next year. I know how many hours I should be working on these Projects each month and I as start the Project I add ...

    Views

    303

    Likes

    0

    Replies

    2
  • 4/18/18
    Hi, I'm not sure if this is possible, but I have a report where I show the date variance between the plannedCompletionDate and the entryDate for one of our partners; however, I've been asked to change the logic to show the variance between the date the Task Status changed to completePendingApproval ...

    Views

    347

    Likes

    0

    Replies

    4
  • 4/17/18
    Rethink the way you manage projects with the new Gantt chart. When you enable edit mode in the Gantt chart, you can make changes to information inside the chart. Prior to this change, you could not edit the information in the Gantt chart, you could only edit task information on the task list. Using ...

    Views

    427

    Likes

    0

    Replies

    2
  • 4/17/18
    Good afternoon all, bit of a stumper here. Our CIO uses a request queue to create issues for himself and has asked if he can add a first status update when he submits the issue. This isn't natively an available request queue field, so I was wondering what custom form magic someone might have. Has an...

    Views

    212

    Likes

    0

    Replies

    3
  • 4/17/18
    Hello all, I'm looking for a means of attaching an image to a project through the mobile app. I'm using the Project version of Workfront, not the Proof version. Essentially we're trying to allow users to attach receipts for expense reporting purposes. Most of our users capture receipts through their...

    Views

    138

    Likes

    0

    Replies

    1