Expand my Community achievements bar.

Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 5/4/18
    Hello All, Is anyone reporting on last time hours were logged against a project? I have a monthly report (Project) that I've been working on with Workfront for several months trying to only pull in projects where no hours were logged for more than 30 days. There is a huge limitation on filtering - H...

    Views

    415

    Likes

    0

    Replies

    6
  • 5/4/18
    Hi all! I am trying to create a report with the timesheet end date. Unfortunately, because of the way we initially loaded the system, some of our data is missing a time sheet end date. So I am trying to use text mode to identify blank end dates and substitute a date of 9/30/2017. This is what I have...

    Views

    214

    Likes

    0

    Replies

    1
  • 5/4/18
    Curious to see if anyone here has integrated their instance with Eloqua and would be willing to share. Thanks! Danya Porter Bloomberg L.P.

    Views

    254

    Likes

    0

    Replies

    1
  • 5/4/18
    At our company we want to only plan to 30 hours of work for our employees and some directors even less. I was thinking of doing this through time off because when we were first configuring our instance we were told not to do this on the default schedule. Although, now that we have been in Workfront ...

    Views

    279

    Likes

    0

    Replies

    3
  • 5/4/18
    Do the System Admin have the authority to over ride the color selections used in Workfront? Benetta Perry APS

    Views

    194

    Likes

    0

    Replies

    2
  • 5/4/18
    Hi , So little bit of background - in our project methodology we've got stages. I would like to pull report which would tell me the number od days spend in between stage 1 and 3. Every single stage has got parent task equally name as the stage. My perfect calculation would be number of days between ...

    Views

    206

    Likes

    0

    Replies

    2
  • 5/4/18
    Our technical writing group obtains approval for policies, procedures, and forms in Workfront Proof. One of our controls is to archive and lock a fully-approved proof. However, the current controls allow any WP user to unarchive a proof. This is a control risk for our group. Is there a way to restri...

    Views

    215

    Likes

    0

    Replies

    1
  • 5/3/18
    I am trying to export a project gantt chart to a PDF and keep getting the following error: java.lang.String cannot be cast to java.util.List I have updated my Java and the scripting is enabled when using IE browser. I get the same error when using Firefox as well. Matthew Luedtke Harken USA

    Views

    153

    Likes

    0

    Replies

    0
  • 5/3/18
    Hi all, I have a calculated custom field to show the number of tasks coming in the Next 0-15 Days, 15-30 Days, 31-60 Days and Over 60 Days. I'm pulling this into a bar chart to show stacked statuses for those buckets. The problem is the columns are not ordering correctly. 15-30 Days is first, follow...

    Views

    259

    Likes

    0

    Replies

    3
  • 5/3/18
    Atlanta Community, Tomorrow is my last day at Kimberly-Clark, as I have elected a voluntary leave package that will allow me to take some time off before I jump back into the working world. Crazy to say, but one of things I will miss most is coming in each day and opening Workfront! I was part of th...

    Views

    141

    Likes

    0

    Replies

    0