The default grouping for Reports is "Folder & Type" I would like a grouping that is just "Type" meaning "Object Type" but there is no option to select Object Type as a grouping, and Report Type groups them into Aggregate, Matrix and List. So how do I group by Object Type, without the folders?
Hi all! I'm in the manufacturing industry. We produce burners for gas appliances. We've been using Workfront for 2.5 years now, mainly for our New Product Development projects. My management is interested in seeing how other manufacturers are using Workfront and picking up some best practices. ...
We have a report that displays all issues we received per quarter but I would also like to include all projects created per quarter within a certain portfolio that don't have an issue attached to them (they started directly as a project not as an issue that was converted). I can't figure out the tex...
With our use case, Projects are reopened sometimes seasonally as more information is added to them that needs to be completed. When we reopen Projects, we adjust the Planned Completion Date to reflect the new deadline. Unfortunately, when trying to build reporting on these dates, it shows the first ...
Our designers & PMs like the look & feel of the WF kanban. However, the vast majority of our work is comprised of rather complicated waterfall projects. Has anyone successfully developed an interface (or report/dashboard) that's modern/clean/colorful and loved by Designers? Alternatively, has anyon...
I want to create a line chart for 1 project that groups the hours by milestone (not individual task) to show the start, finish and hours across a long term project so we can demonstrate the season peeks by milestone. Is this possible?
I have a Documents report that lists all documents from all Projects within a Program.I want to make the column Project: Converted Request Name a clickable link so user can easily get to the originating Request.I tried the code from this discussion, but unfortunately, it did not work.Any help is app...
Hello - Is anyone aware of a work-around to pull Issues into a typeahead field on a custom form? Currently, you can't pull this object type in. I want a field where a requestor can reference a previous request they submitted. Thanks for any suggestions.
Hi WF Community, Does anyone know of a way to create a custom field on the Task object that will do the following? Capture the Planned Completion Date value in this new field, and don't overwrite this value if the Planned Completion Date field value is updated after its initial value. I know how to ...