Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
Sort
  • Most recent
  • Most views
  • Most likes
  • Most replies
  • Oldest First
Filter
  • All
  • Resolved
  • Unresolved
  • Zero replies

  • 4/14/23
    Is there a way I can REQUIRE users to assign their projects to a Portfolio? My only solution is to force them to use a Project Template and preassign the Portfolio there. Any other solutions?

    Views

    623

    Likes

    0

    Replies

    6
  • 4/14/23
    Hi- I'm trying to compare two dates in a Workfront report via conditional formatting.  Whenever the target launch date is less than the Planned Completion Date, the background for the Target Launch date item should be in red. When the report loads, the background for the dates that are less than AND...

    Views

    424

    Likes

    0

    Replies

    3
  • 4/14/23
    We have large project plans and have some specific tasks that run the entire lenght of the project to allow users to log time to. Trying to find a way for those specific tasks not to affect the project condition. As those tasks are really place holders for time and don't get updated that often. But ...

    Views

    609

    Likes

    0

    Replies

    5
  • 4/14/23
    Hi there! We're getting ready to rollout Workfront to our company, and one thing we've been trying to figure out is how to set a default *custom* view for a specific client project, for that specific working team. We understand how to share views with certain teams/groups, but can we take it a step ...

    Views

    534

    Likes

    0

    Replies

    4
  • 4/14/23
    Has anyone tried this?  Can you show examples/screenshots?  Monday.com seems to do this well, but I'm not sure if Workfront has the capability.

    Views

    3.0K

    Like

    1

    Replies

    6
  • 4/13/23
    Is there a way to see current proofs list pending approval on only active (in progress) projects?

    Views

    793

    Likes

    0

    Replies

    4
  • 4/13/23
    Is it possible that each request type had their own form and based on the Request Type Workfront would only select the form associated to that request type.

    Views

    395

    Likes

    0

    Replies

    1
  • 4/13/23
    Is there a way to add multiple columns at one time when creating a report without having to select the + Add Column button after clicking on each column item you want to add? In example, in the attached photo, I want to add in the highlighted columns to my note report : Entry Date, Has Replies, ID, ...

    Views

    295

    Likes

    0

    Replies

    1
  • 4/13/23
    Hi guys -  We are currently only using projects in Workfront and I'd like to get us to start using more of the organizational hierarchy. Currently we track multiple deliverables in 1 project, but sometimes items that should be associated with that same work effort are then created in a secondary pro...

    Views

    3.9K

    Like

    1

    Replies

    15
  • 4/13/23
    Hello,I am trying to figure out how to add a percentage complete column at the project level based on Actual Project Hours versus Planned Project Hours.This would be different than the regular built-in percentage complete, which doesn't work for us based on the way we set up our projects.For example...

    Views

    481

    Likes

    0

    Replies

    3