    This is the last call for proofing questions, comments, input, feedback for the UX team who will be on "https://one.workfront.com/s/question/0D50z00006Px4gNCAR/">this thread in the Community today providing input and getting insights for the ProofHQ tool! "https://one.workfront.com/s/question/0D50z0...

    Views

    102

    Likes

    0

    Replies

    0
  • 8/1/17
    Hi, Is there a way to re-create Team Resource Grid as a report? Ideally i would like to change a bit shape of it. Need to get ,matrix grouping to get project name on the left, and then by user/by week on the top. Is it even possible? been looking around reports but haven't gotten to anything similar...

    Views

    259

    Likes

    0

    Replies

    4
  • 8/1/17
    Could some of you share your experience with custom help sites you have set-up to help your internal team onboard Workfront? What do you use? Anyone using Google sites? Delphine Campes-Edouard Pluralsight

    Views

    134

    Likes

    0

    Replies

    0
  • 7/31/17
    Hi all - I am trying to create a listing of scheduled reports, which seems to be a straight-forward task, but I am unable to generate any meaningful results. Can some one help please? Adding a filter to a standard Report report for Scheduled Report >> ID Is Not Blank delivers an empty report. Cheers...

    Views

    425

    Likes

    0

    Replies

    5
  • 7/31/17
    Hey everyone, don't forget that tomorrow ( Tuesdsay ) we'll be having an "https://one.workfront.com/s/question/0D50z00006Px4gNCAR/">AMA with UX Designer over the Workfront proofing tool, Skylar Sanford . Get your questions in early so we can start prepping some thoughtful responses! "https://one.wor...

    Views

    116

    Likes

    0

    Replies

    0
  • 7/31/17
    We are new to Workfront and just wondered if it is possible to version control a plan in workfront so that a previous version can be re-instated. If so how do you do this ? Philomena D'Sa Engie

    Views

    391

    Likes

    0

    Replies

    5
  • 7/31/17
    Hi everyone. We are a product development company and have multiple people working several different tasks for several different customers (often simultaneously) . This means that our staff have to add/remove tasks from their timesheets on a regular basis. What is the easiest way to do this? Current...

    Views

    187

    Likes

    0

    Replies

    2
  • 7/31/17
    I'm sure this will result in a "slap my head, that should have been obvious" moment but I'm struggling on how to generate a report that shows users who posted no hours in the preceding week to a selected set of projects (have projects tagged in the project description field). I know I'm just missing...

    Views

    160

    Likes

    0

    Replies

    1
  • 7/31/17
    Hey everyone, don't forget that tomorrow ( Tuesdsay ) we'll be having an "https://one.workfront.com/s/question/0D50z00006Px4gNCAR/">AMA with UX Designer over the Workfront proofing tool, Skylar Sanford . Get your questions in early so we can start prepping some thoughtful responses! "https://one.wor...

    Views

    142

    Likes

    0

    Replies

    0
  • 7/31/17
    I've noticed that only those assigned to a task can complete the custom form on that task. We want designers to be able to complete a custom form on the Production manager's task without adding them to the task as well (they have enough tasks already). Is there some way to edit their access to allow...

    Views

    530

    Likes

    0

    Replies

    6