  • 5/24/24
    I know this is a sharing issue with a project template but I'm not how to correct it. Every time a project is created by a specific template, the entire team gets a notification. Is it because the template is shared with the team or is it because the template has the project sharing setting shared w...

    Views

    489

    Likes

    0

    Replies

    4
  • 5/24/24
    Is there a way to create a report at the user level that would show which queues, reports, dashboards, etc., an individual has access to? I know I can look at the sharing on the queue, report/dashboard, but we're trying to create a "persona" report showing how different types of users have access to...

    Views

    276

    Likes

    0

    Replies

    1
  • 5/24/24
    I need help making a report with a chart. I am trying to make a report on a specific person and if their task is completed on time and if it's not complete show up as not done and late. There are two people assigned to this one task. What I want is to only make the report on one of those people and ...

    Views

    360

    Likes

    0

    Replies

    1
  • 5/23/24
    Can you set custom statuses for billing records? Right now all I see are 'Billed' and 'Not billed'. I haven't been able to track down an area where you can add more. Am I just missing it, or is it not possible yet? 

    Views

    285

    Likes

    0

    Replies

    1
  • 5/23/24
    Our users are not receiving notifications when a decision has been made on a proof they've created. What settings do I need to adjust to resolve this? 

    Views

    280

    Likes

    0

    Replies

    1
  • 5/23/24
    Hi All, I'm trying to create a custom column on a project report that will display all active parent tasks in a project, along with the % complete. How would I go about creating a text code that would generate this for me?

    Views

    628

    Likes

    0

    Replies

    5
  • 5/23/24
    Hi All, Our current project form manages approximately 200 custom fields of various types, many of which are supported by logic. Over time, we've realized that we need to limit the complexity to maintain smooth performance. I'm curious about how others handle larger and more complex sets of custom d...

    Views

    810

    Like

    1

    Replies

    6
  • 5/22/24
    I'm trying to convert an issue to a project, attach a template to the project, and keep all custom forms and data associated with them. I can't seem to get the custom forms from the issue and their data to transfer over. At first I tried using the "Convert Object" module but after reading a previous...

    Views

    568

    Likes

    0

    Replies

    5
  • 5/22/24
    I have seen a few older posts about this but it is not working on a report I am doing. It is in a task report and is filtered to look at a specific task completion. I have tried custom column:displayname=Submission to CCB Decision Turnaround Timetextmode=truevalueexpression=WEEKDAYDIFF({convertedOpT...

    Views

    564

    Likes

    0

    Replies

    4
  • 5/22/24
    I'm using this text mode to see the actual completion date of the Strategy task, but the task is a parent task and it's not pulling in. Is there a different label to pull in parent tasks?  displayname=Strategy Complistdelimiter=<p>listmethod=nested(tasks).liststextmode=truetype=iteratevalueexpressio...

    Views

    596

    Likes

    0

    Replies

    4