I am looking for the best way to share a Gantt chart with the sponsor that doesn't look bad. I know there is the calendar report option, but this doesn't look all pretty and show items like predecessors, so will not work. I know i can share a timeline report externally, but this does not include a G...
I am looking for the best way to share a Gantt chart with the sponsor that doesn't look bad. I know there is the calendar report option, but this doesn't look all pretty and show items like predecessors, so will not work. I know i can share a timeline report externally, but this does not include a G...
The Task Report doesn't filter the right people I need for the report so I made an Assignment Report for one Department Head who is WF-challenged and really hates marking tasks done or assigning people to tasks - these are the only things she has to do. I need ONE report that is interactive where sh...
Here’s our use case: We created a job role and added a billing rate.We assigned a worker (user) that job role with billing rate.Worker with the job role is assigned tasks in projects.Then Worker with job role logs hours and there are actual revenue for project (hours times billing rate for job role...
I don't know where to put in a bug report, or maybe this is a feature issue. When adding a range of custom dates into a calendar to populate tasks, it seems that both the start and end (or date 1 and date 2) must be populated -- otherwise the task won't populate. Why is this an issue? Let's use a re...
Please upvote if you think it would be handy to be able to automatically discard the previous message on a proof.https://one.workfront.com/s/idea/0870z000000XiHXAA0/detail
Out Fiscal Year runs from July 1 through June 30, and at no point is the planner explicitly asked what fiscal year a project falls into. I need a field that will calculate what fiscal year a project is in based in the creation date of the project (close enough for my reporting needs). I planned to p...