Hi community, I'm trying to find the best work-around for adding an existing WF document as a new proof version to an existing proof. I'm trying to avoid downloading and then dragging back in. ThanksMatt
Hi to All, Anyone can help / suggest from your expertise to create below type report.The planned and actual hours for all the tasks my team (per team member) worked on (actual hours) last week. I want to group it by Project Name.What type of report is the best or need to create any custom field? Reg...
Is there a way to only notify the task owner when its task predecessor is Complete? Example:Design ad> Launch ad (Do not show this to the task owner until Design ad is complete)
Is there a way to add an approval process for certain tasks in Task Template?For e.g.Design ad (Requires approval)Launch ad (Does NOT require approval)
We currently use a custom integration to move files from Workfront into AEM Assets (Cloud). In Assets, we have a multi-folder structure. Is there a field within Workfront that captures the location of where the document has been moved to? I use the documentProviderID to capture "AEM" but I'd also li...
Hi all, in a video embedded in this Adobe post, under "Differences Between Legacy Workfront...." [thanks Morgan :)] there are changes to current nav vs. what we have in our current instance. I've asked Adobe several times to help us prepare for migration, especially to prepare our users for what to...
Has anyone sent any communications about the upcoming change from worklist to the New Home Workspace to their users? Specifically, looking to make them aware of the change, offer to answer any questions, and to inform them not to use it until we provide more information. (in a nicer way, of course) ...
I am struggling with reports. I need to have one report that shows all tasks and request that have been assigned to a team so that the manager of the team can distribute the work. I have been trying to use the Assignment report but I can't figure out the columns so that I can see the request. Ques...
Good morning all,Myself and my colleagues have recently noticed that the months are not displaying on the Gantt chart view of any project we work on. As it has affected several of us, i assume this isn't a user error, but potentially a system change that has caused this.Does anyone know how to displ...