How to only notify or show task when predecessor is Complete?

Avatar

Level 4

Is there a way to only notify the task owner when its task predecessor is Complete?

 

Example:

  • Design ad
  • > Launch ad (Do not show this to the task owner until Design ad is complete)
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 6

Hi @stan255 

 

You can do so using a report and filter on Can Start (or use the filter in the task View)

 

Also check out the filters on the Home/Workspace widgets (eg My Work has a "ready to start" filter)

View solution in original post

2 Replies

Avatar

Correct answer by
Level 6

Hi @stan255 

 

You can do so using a report and filter on Can Start (or use the filter in the task View)

 

Also check out the filters on the Home/Workspace widgets (eg My Work has a "ready to start" filter)