Is there a way to only notify the task owner when its task predecessor is Complete?
Example:
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Hi @stan255
You can do so using a report and filter on Can Start (or use the filter in the task View)
Also check out the filters on the Home/Workspace widgets (eg My Work has a "ready to start" filter)
View solution in original post
There is also this setting