How to only notify or show task when predecessor is Complete? | Adobe Higher Education
Skip to main content
Level 4
October 15, 2024
Répondu

How to only notify or show task when predecessor is Complete?

Is there a way to only notify the task owner when its task predecessor is Complete?

 

Example:

  • Design ad
  • > Launch ad (Do not show this to the task owner until Design ad is complete)
Ce sujet a été fermé aux réponses.
Meilleure réponse par Sven-iX

Hi @stan255 

 

You can do so using a report and filter on Can Start (or use the filter in the task View)

 

Also check out the filters on the Home/Workspace widgets (eg My Work has a "ready to start" filter)

2 commentaires

Sven-iX
Community Advisor
Sven-iXCommunity AdvisorRéponse
Community Advisor
October 16, 2024

Hi @stan255 

 

You can do so using a report and filter on Can Start (or use the filter in the task View)

 

Also check out the filters on the Home/Workspace widgets (eg My Work has a "ready to start" filter)

RandyRoberts
Community Advisor
Community Advisor
October 16, 2024

There is also this setting