Hi All, I'm trying to figure out a way to create a custom field that lives at the parent task level that sums up a custom field that is associated with each child task of the parent. I've been using the SUM function but I'm not sure how to reference the child tasks in the formula. Any help is g...
Hello, Is there a way to upload a list to populate the form dropdown choices. We would like to have the user select from a list of clients, but the list is well over 1,000. Entering and managing that list in the Workfront form is not sustainable. Also, once we have this we want to share the field ...
Hello, I created a task report with two groupings to show Company -> Program -> Projects -> Tasks Now I want to filter out all inactive programs. Therefore I added the following code to the textmode. project:program:isActive=true project:program:isActive_Mod=eq Unfortunately this leads to a...
Dear community members, I want to check whether all colleagues with a Planner license currently manage projects. So, I'm looking for a user report that filters all colleagues with a Planner license and one (nested) column will give me the projects that that user is the owner of. Does anyone ha...
Hi there - hoping someone has some insight into this issue / question: - Notifications - we are receiving notifications via Fusion that a new project has been created. However, we have a series of templates, and only need certain individuals notified when those templates are created (not all of th...
Hi guys, fairly new to Workfront (< 6 months) so apologies if this is a question that has been asked before A PM within the team wants to create a new project template but is struggling to make it work with regards to tasks starting and completing on set days. For example, Task 11 - Styling session ...
Is there a way to track the duration of time a project has spent in the "On Hold" Status? If its two separate formulas I know I can use a third WEEKDAYDIFF formula to calculate the duration, but I'm not sure how to get the time stamps of when the project went "On Hold" and when it came off of "On H...
I am trying to run a report filtered according to who the object is shared with (e.g. Shared with X Group or System-Wide) but I do not know how to add that as filter. I have the "shared-with" field in my view so I know I can get at the data but struggling to filter on it. Any help appreciated!