Is there a way to mass update an entire project to a specific Duration Type? I ask because my Resource Leveling is no longer working and I am thinking one of the Tasks may have been set to Effort Driven. I know Resource Leveling is a delicate function, are there any other possible reasons Leveling i...
We track CAP budget based on what hour type is used on the resources timesheet. Is there a calculated field I can use to say CAP actual cost = sum(all timesheet costs where hour type = 2 - 6) and EXP actual cost would be sum(all timesheet costs where hour type = 1 or 7)? Anyone know how to do this? ...
Hello, Not sure if Workfront has this feature. I have never been able to find it in the tutorials. Is there any way a reminder can be setup for annual projects? For instance if we do a yearly annual report or magazine and want a notification sent to me or the project manager notifying us that around...
Hello Everyone, I am starting to experiment with converting issues to tasks-only rather than projects if it is a simple one-off. However I seem to struggle with changing the due date each time. It always takes some jockeying (which defeats the purpose of trying to make it quicker). For instance if t...
Interested to know if anyone is using Workfront to manage things like staff reviews and personal development? I'm currently building out some processes - a combination of projects, request queues, custom forms and dashboards - and would be good to hear if anyone else has any tips or insights. Thanks...
Hi All, We have been using workfront for a while now, one of the functionality we knew wasn't there but was told it would be soon, was scenario planning or modelling. Each year during business planning i need to be able to impact the total cost internally and externally of the pipeline. I need to be...
Hi Group! I have a simple question - if I change a field type (from a radio button to a checkbox or vice versa) will I lose the data already stored in those previous fields? The choices presented in each field would remain the same. After building and using a custom form, with some new fields - I ju...
The 'standard' way of managing financials in Workfront is by using the standard fields: Budget, Estimate at Completion, Fixed Cost etc: I'm wondering -- for those people who have decided that they need to create their own financial fields (either in conjunction with the out-the-box fields, or as a c...
Hi Community! Last week my manager and I held a meeting that we called the "Workfront Power User Idea Exchange." (we borrowed the Idea exchange theme for an hour, hope that's okay!) Our "Power Users" are the workers, planners and system administrators that represent the following departments at Dive...
I've been asked to import a number of projects from Excel. I've used the kickstart feature many times, but I'm having difficulty. I've been asked to import the planned start dates and the task durations. I'm able to import the tasks, but the start dates and durations are not set. I filled in the fol...