Hi, Commit Dates are really killing us and causing a lot of confusion/frustration with users. e.g. A task is originally scheduled for a certain date and an assigned user clicks 'Work On It', Workfront sets the commit date to the planned date (assuming the user doesn't propose an alternative comm...
Hello - Is is possible to customize milestone reports? I would love to take off the start date (for some reason projects are appearing as late even if the tasks are started on time) and add a grouping. Thoughts? Thank you!
We are using request queues for more and more and find them great to get requests to the right people and into the correct "project" or holding queue. The one challenge we've had is when a user selects an incorrect queue topic. It is easy enough to move the issue and assign it to the correct perso...
I am trying to find a way to have Outlook meetings pushed into Workfront. We are using Single-Sign On. We need to be able to see how much meeting time a person has on any given day whe allocating resources for a project. We are the only department in our company in Workfront. The company uses Outl...
Hi. I'm looking for direction on how to create a utilization report. We are a creative services team made up of project managers, writers, editors, designers and myself, production. We are not a revenue generating business unit. However, we produce over 2,000 projects per year (print, digital, editi...
In a project report, I need a custom column labelled as a particular month (June '16 for example) that searches within it's project task list for two sets of criteria: 1. The task has a custom form field called 'Type' applied to it 2. The planned completion date of the task finishes within a dat...
We are trying something new out where we are doing weekly status updates on a custom form attached to a task. Each week, the PM will create a new task for their status update, add the custom form and then fill out the fields of what they did this week, whats next week, etc. That part all works fine....
I need to create a chart report that displays each Job Role FTE total (stacked) within each Work Week (work week on X Axis). Has anyone got any suggestions for me? I've tried a few times myself but am not getting very far with any of the types of reports I have built. Help is greatly appreciated...
I've been studying a few text mode code samples that feature the SHARECOL=true command. I'm stymied now.I can't figure out why sometimes an attribute stays in the same column and sometimes it gets its own column. I haven't misspelled the command. If I move elements of the report around (and renumber...