Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
SOLVED

What does the number displayed for "Project First Duration" represent?

Avatar

Level 7

Screen Shot 2022-09-06 at 1.22.13 PM.pngI am following Example of Velocity Reporting, August 14, 2019  - so, a lot of calculation - planned vs actual vs baseline (first duration) - but it doesn't display number of days or hours - calculations are working but I can't explain what is being pulled in reality 

 

Work-to-Commit Ratio Format:Number Calculation: ROUND(DIV(Actual Duration,First Duration),1)

 

see screen shot(s) - first duration column is just allowing a number of percentageScreen Shot 2022-09-06 at 12.58.57 PM.pngScreen Shot 2022-09-06 at 12.57.50 PM.pngScreen Shot 2022-09-06 at 12.58.31 PM.png

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Tegwyn, it looks like that First Duration is a custom field.  You would need to look under custom reports->fields to see what information it might be pulling.

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Tegwyn, it looks like that First Duration is a custom field.  You would need to look under custom reports->fields to see what information it might be pulling.