Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!
SOLVED

What does the number displayed for "Project First Duration" represent?

Avatar

Level 7

Screen Shot 2022-09-06 at 1.22.13 PM.pngI am following Example of Velocity Reporting, August 14, 2019  - so, a lot of calculation - planned vs actual vs baseline (first duration) - but it doesn't display number of days or hours - calculations are working but I can't explain what is being pulled in reality 

 

Work-to-Commit Ratio Format:Number Calculation: ROUND(DIV(Actual Duration,First Duration),1)

 

see screen shot(s) - first duration column is just allowing a number of percentageScreen Shot 2022-09-06 at 12.58.57 PM.pngScreen Shot 2022-09-06 at 12.57.50 PM.pngScreen Shot 2022-09-06 at 12.58.31 PM.png

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Tegwyn, it looks like that First Duration is a custom field.  You would need to look under custom reports->fields to see what information it might be pulling.

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Tegwyn, it looks like that First Duration is a custom field.  You would need to look under custom reports->fields to see what information it might be pulling.