Michelle, does Project B exist before Project A reaches the task that Project B is dependent on? If not, is it possible? If so, I agree with Heather's recommendation. This is the way I typically suggest handling the need to notify that necessary work from another project has been completed. This unfortunately can't be set up by template, as the cross project predecessor is set up using a project ID. It would require that the project planner for Project B sets this up when they create their project. Parker Cantu