Level 4

Is there a way to create a report for an existing capacity planner for a certain period (6 months+) showing the workers overall capacity and free time?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

We use Resource > Planner for this. There are some limitations and criteria to make planner work but we like that it shows available, planned, actual and % allocations for users.

 

Sample of what it looks like: