Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.
SOLVED

Report for workload balancer?

Avatar

Level 4

Is there a way to create a report for an existing capacity planner for a certain period (6 months+) showing the workers overall capacity and free time?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

We use Resource > Planner for this. There are some limitations and criteria to make planner work but we like that it shows available, planned, actual and % allocations for users.

 

Sample of what it looks like:

KellieGardner_0-1706713942958.png

 




View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

We use Resource > Planner for this. There are some limitations and criteria to make planner work but we like that it shows available, planned, actual and % allocations for users.

 

Sample of what it looks like:

KellieGardner_0-1706713942958.png

 




Avatar

Level 4

Super helpful! Thank you!