  • 10/11/19
    I'm trying to figure out how to configure our proofs so that the proof owner isn't getting so many emails. We have the designer upload the proof and send it through an automated proof cycle. Originally we were having the designer use the setting of "all Activity" so they were notified of everything ...

    Views

    279

    Likes

    0

    Replies

    4
  • 10/11/19
    I'm trying to capture date and time in a calculated custom form, as it describes here: https://experience.workfront.com/s/article/Understanding-Common-Uses-of-Text-Mode-37391990#calculated-custom-fields Was able to copy the example in that Help section almost exactly. I'm trying to get the date/time...

    Views

    252

    Likes

    0

    Replies

    2
  • 10/11/19
    Hi, Can someone please help out with the Project Form? I have added all the info from the Request Form to the Project Form but it is not showing up on the form when someone submits a request? Not sure what I'm doing wrong. thanks Jennifer Jennifer Miklasz Fidelity International

    Views

    261

    Likes

    0

    Replies

    3
  • 10/11/19
    Hello, Is there a way to create a custom field on a custom form that will list all active projects? Preferably a type ahead, or a drop down. Curtis Gifford Kronos

    Views

    280

    Likes

    0

    Replies

    4
  • 10/11/19
    I'm trying to make a form/approval workflow that based off a dropdown box will choose which way the form approval goes. The form has a department dropdown box, which is called 'Cost Centre'. The approver needs to change based off which department is picked, not just the manager of the person. I can'...

    Views

    128

    Likes

    0

    Replies

    0
  • 10/10/19
    is there a simple way to show duration in weeks as calendar weeks? If I put in 26w starting January 1st, I get Sept 20 as a finish date. I was expecting end of June. So obviously a week is calculated based on 7 work days not 5 work days. Other PM programs (like MS Project) show weeks as calendar wee...

    Views

    189

    Likes

    0

    Replies

    1
  • 10/10/19
    Our design team are all on Macs - they have issues when they receive these comments, they click and can't go right to the comment - it takes them into the general job area and they don't know what is being commented on. They are on Outlook. Some of them also don't receive comments unless they are sp...

    Views

    173

    Likes

    0

    Replies

    1
  • 10/10/19
    Hi Community! Does anyone know if it is possible to filter by comparing dates, where the comparison ignores the time portion of the date and compares the date itself only? I am using Text Mode: projectedStartDate=FIELD:plannedStartDate projectedStartDate_Mod=gt However, this doesn't give me precisel...

    Views

    142

    Likes

    0

    Replies

    0
  • 10/10/19
    Is there a way to automatically adjust a project timeline based on an assignee's workload? For example: One person puts in three issues, when I convert the issues to a project and assign the tasks, the due dates for the tasks are automatically based off of the planned start date, and they all fall...

    Views

    164

    Likes

    0

    Replies

    0
  • 10/10/19
    Is there such a thing? I'm looking at the user* objects on the API explorer and I've not come across this. What I'm hoping to do is automate an add user request and auto create the user based on a default user account that I have. While I can manually write code to select each feature for the user a...

    Views

    167

    Likes

    0

    Replies

    1