I uploaded this file to the Global Discussion group earlier using the "Share a File" feature, but don't see anywhere in the Community where it actually posted. So, I'll just add a topic. A popular feature request in the Idea Exchange is to display user's initials as their avatar if they have not upl...
Hi, We keep running into an issue at our agency with shared deliverables that should have two different deadlines. It would seem logical that we set up two tasks with task 2 dependent on task 1, but there's a semi-complicated issue with that. All of our tasks are dependent on an approval process. If...
Looking for help or advice. When using the Kanban view for an agile team. Can we customize the column names (status names) to be what our team needs (we don't want to change the statuses for the entire organization - just for our team)? Has anyone else come across this problem? thanks!
Hi WF Community! Has anyone noticed a change in the order of events or the format leading up to the releases? From what I remember, Workfront used to hold the live webinars first, then they would release each beta stage to the sandbox. Now, the beta releases are in the sandbox before the webinars ...
Hello ~ There is an area within Workfront that lists the options of what happens when a task is complete or an issue is complete. Anyone know where that is located? Thank you. Susan
I have a bunch of Tasks that should take no more than 10 days, but as we all know sometimes Tasks take longer and sometimes not. What I want to do is create a Report, with a chart, that shows me the percentage of Tasks that take less than 10 days and more than 10 days. How can I create this Report? ...
Hi, I'm working with the API for some time now and i there is a question that i can't find an answer to. How can i duplicate a task more than once with one call (bulk duplicate/copy)? I managed to copy it with the copyBulk action but only one by one (tried to put the task ID twice in the list but it...
Is there a way on a report to display a count of the # of users currently assigned to a task? Essentially I want to use that to set up another custom field so that users can see their allocation in a report. E.g. Bob, Jim, Kyle are assigned to a 3 hour task. The calculated assignment will measure th...
We're excited for the next meeting of the Atlanta User Group, hosted by Children's Healthcare of Atlanta on Feb. 16, 2018! "http://lp.workfront.com/AtlantaQ12018UserGroup.html">Registration is live . Take a minute to let us know you're coming. Carol-Lyn Jardine Workfront
Hi all, As per the documentation, projects' net values come from the business case and are calculated as follows: Project Net Value = Planned Benefit - Budgeted Cost - Potential Risk Cost We don't commence our projects from a business case, and so the planned revenues and costs are not entered there...