    We can transfer scenarios using the blueprint export/import. However, we can't seem to do the same with data structures. I know it's possible to generate the data structure using example JSON, but if that's not available, we have to create it all from scratch. Perhaps it would help if there was a wa...

    表示

    426

    いいね!

    0

    返信

    3
  • 2025/04/15
    Hey all - I just created a ticket for this and wanted to check - do you see this as well? Or is it just my client's environment: The update module shows non-editable fields as text boxes... (When I select "attach custom form")  

    表示

    373

    いいね!

    0

    返信

    3
  • 2025/04/14
    Hi team, We integrated Worfront to JIRA using Fusion. We create JIRA tickets using automation, which generates a payload that we load in the JIRA description based on the fields filled in an Intake Form.We are having trouble formatting this payload. Is there a way to send bold text through Fusion?I ...

    表示

    244

    いいね!

    0

    返信

    1
  • 2025/04/09
    Can anyone pls share Adobe workfront fusion design template document to use in projects

    表示

    693

    いいね!

    0

    返信

    8
  • 2025/04/09
    Hi, I’m stuck on something - how do you use Fusion to subtract x days from a planned completion date? I can see there’s an addDays function, but nothing for subtracting. Is there a workaround for this? 

    表示

    284

    いいね!

    0

    返信

    2
  • 2025/04/09
    Hi All, Is there any way to trigger a watch event when user Access Level change automatically. I know we can use Joural Entry but I can't filter by UserName=System. Any Idea! Thanks in Advance

    表示

    318

    いいね!

    1

    返信

    4
  • 2025/04/08
    I want to build a scenario that looks at a project's tasks to see if they are complete. The project can have up to 3 specific tasks with set names that need to be completed. Is there a way I can accomplish this using custom fields while still using an instant webhook event? Like something along the ...

    表示

    225

    いいね!

    0

    返信

    2
  • 2025/04/07
    In our instance most Request Queues are available system wide but the requests are routed to a landing project that the team working on those requests have manage access along with contribute access for the individual that made the request.The requesters teams would like to see and contribute to any...

    表示

    285

    いいね!

    0

    返信

    2
  • 2025/04/07
    I have 2 custom fields that I use a watch events module to filled in whenever certain tasks are completed.  This works for projects going forward but I need to fill in the custom fields values for active projects where these tasks have already been completed.  Is there to way regularly loop through ...

    表示

    396

    いいね!

    0

    返信

    4
  • 2025/04/06
    Hi everyone, I need some assistance with sharing projects in Workfront. We have around 700 projects, and I have a list of these projects along with the teams they need to be shared with in CSV. Could anyone guide me on the best way to efficiently share these projects with the respective teams? I can...

    表示

    352

    いいね!

    0

    返信

    2