When we initially set up our Workfront instance, we built the templates around common end deliverable or campaign type (integrated, social-only, creative update, video production, etc).
We have a large client roster, all with very specific ways of working and project needs. To help the PMs have a good starting point we've set up individual templates for client / need, while also having some generic "any client" templates. This seemed like a good idea at the time, but our list of ...
That's what I initially thought too, but I've cross-referenced a couple offender projects, as well as spot-checked a handful of other projects that are abiding by the schedule, and they all have the default schedule applied at the project level.
We have a default schedule set up for Mon-Fri working days, but some of the projects are spreading hours for certain resources onto Saturdays and Sundays. This isn't consistent across all projects or resources, and I've now triple-checked the default schedule. Does anyone know why this might be ha...
Within each of my reports, under the 'Assignment' column, this is the code I have input within text mode:descriptionkey=assignmentsisInlineEditable=falselinkedname=directnamekey=assignmentssection=0shortview=falsestretch=0tile.name=component.assignmentslisttype=tilevaluefield=assignmentsListStringva...
Yes! I have four reports set up and then included in a single dashboard for an all-up view (called My Direct Report's Tasks). These are the four report names I have used:- My Direct Report's Tasks Due Today or Overdue Tasks- My Direct Report's Tasks Due This Week- My Direct Report's Tasks Due Next...