When we initially set up our Workfront instance, we built the templates around common end deliverable or campaign type (integrated, social-only, creative update, video production, etc).
We have a large client roster, all with very specific ways of working and project needs. To help the PMs have a good starting point we've set up individual templates for client / need, while also having some generic "any client" templates. This seemed like a good idea at the time, but our list of ...
That's what I initially thought too, but I've cross-referenced a couple offender projects, as well as spot-checked a handful of other projects that are abiding by the schedule, and they all have the default schedule applied at the project level.
Within each of my reports, under the 'Assignment' column, this is the code I have input within text mode:descriptionkey=assignmentsisInlineEditable=falselinkedname=directnamekey=assignmentssection=0shortview=falsestretch=0tile.name=component.assignmentslisttype=tilevaluefield=assignmentsListStringva...
Yes! I have four reports set up and then included in a single dashboard for an all-up view (called My Direct Report's Tasks). These are the four report names I have used:- My Direct Report's Tasks Due Today or Overdue Tasks- My Direct Report's Tasks Due This Week- My Direct Report's Tasks Due Next...