Risk

Avatar

Level 2

How to link risks to tasks within a project plan

1 solution acceptée

Avatar

Réponse correcte par
Community Advisor

 

Hi @Aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug 

Voir la solution dans l'envoi d'origine

1 Reply

Avatar

Réponse correcte par
Community Advisor

 

Hi @Aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug