Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Risk

Avatar

Level 2

How to link risks to tasks within a project plan

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

 

Hi @Aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

 

Hi @Aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug