Expand my Community achievements bar.

The Community Advisors application is now OPEN for the second class of 2024. Apply to become a part of this exclusive program!

PTO indicator on task assignments

Avatar

Level 5
Hi All, See attached screen shots. Is there a way to add a visual queue to task assignments that indicate PTO during the task duration? I think that would be helpful to our PM's. tks! Karen Karen Rutz Harvard: Alumni Affairs & Development
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 8
A new feature released in 19.3: The little blue information icon against people's names indicates they have personal time off within the duration of the task or issue you're assigning. https://experience.workfront.com/s/article/Enhancements-Releasing-Prior-to-the-General-2019-3-Releas... Barry Buchanan - WMA Work Management Australia