Proof deadlines not accounting for Holidays

Avatar

Level 3

Hello Everyone,

We only use automated workflows with Proof templates and set deadlines. Proof does not account for the holiday schedule, We have to create views in Proof for each holiday and The deadline needs to be manually updated for each stage in the Proof. There is not a way to update this in bulk.

We have been looking for a way to integrate the Holiday Schedule from Workfront within Proof.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10

Hi Julia - at the moment, Proof does not look at the schedules in Workfront so doesn't have the info.

However, I know the product team has been researching for some time and looking to implement later this year (potentially) a solution where the proof workflows are living in Workfront itself. Once in Workfront, it should be able to read the schedule attached to the project and count Holidays.

Obviously, this is just a hypothesis, but getting the workflows for proofs in Workfront and integrating the tool more will be really helpful to achieving this dream!