Hi Here are some thoughts Always select project actions, recalculate timeline when dates don't look right. Projected dates are calculus based on, essentially , burn rate. The planned hours are zero. There is nothing to burn so the work should start and do on the same day I would add some planned hours just to see if the projected dates push out. Hope that helps somewhat . Eric Lucas Eric MPM eric.lucas@crowley.com Crowley Information Technology