Expand my Community achievements bar.

ThereseGr
ThereseGr
Offline
Type
  • All
  • Questions
  • Discussions
  • Ideas
  • Blogs
Filter by user contributions
  • Big problem today. I will try changes in the Sandbox, but you can't transfer the changes to the live version and the snapshot is only once a week so I lose any updates between the snapshot and the day I do the modeling. Another way to do this could be some version of Save As. Copying all the tasks o...

    Type

    Ideas

    Views

    327

    Likes

    0

    Replies

    0
  • Please vote on this idea to change the duration type in the project details screen. https://support.workfront.com/hc/en-us/community/posts/360008013574-Project-Duration-Type-Add-Ability-to-Change-in-Project-Details Therese

    Type

    Questions

    Views

    1.1K

    Likes

    0

    Replies

    0
  • Our system uses "Calculated Assignment" as the default duration type for new projects. That setting is appropriate for the proof projects that are managed through Workfront. However, for non-proofing projects, other duration types may be better. I have found that changing the duration type from Cal...

    Type

    Ideas

    Views

    150

    Likes

    5

    Replies

    1
  • I want to show how much the project has changed since I created my baseline. I'm primarily looking to show the projected start/finish, which reflects current timing, and the baseline start/finish. I can add the projected start and finish dates to my report. Does anyone know how to include the baseli...

    Type

    Questions

    Views

    243

    Likes

    0

    Replies

    2
  • None of these worked. I found another task that has the same issue. It is really messing up my critical path information. Therese

    Type

    Questions

    Views

    353

    Likes

    0

    Replies

    0
  • I have a task that is supposed to start in 2019. The duration is 6 weeks and the Planned Start/Finish make sense. However, the Projected Start/Finish are the same date, so essentially a 0 day duration. See my screen shot from the task details. Any ideas on what happened or where I can look to fix it...

    Type

    Questions

    Views

    353

    Likes

    0

    Replies

    5
  • One more thing to add; work with support to create custom views that give you the functionality you need. For me that has been getting a successor column. I'm working on getting days of slack/float. There is no way to get the network diagram in Workfront. That is the last thing I really miss. Theres...

    Type

    Questions

    Views

    1.2K

    Likes

    0

    Replies

    0
  • I worked with the main Planview solution a few years ago, both as a project manager and system administrator. It has a lot of capabilities, but you pay for those in administrative overhead, we had to dedicate headcount to keeping it current. The native reporting was not good. The nice reports and da...

    Type

    Questions

    Views

    855

    Likes

    0

    Replies

    0
  • I am asking you to upvote a request to make the number of days of float available as a field that can be added to a report. https://support.workfront.com/hc/en-us/community/posts/360002029654-Add-Field-for-Days-of-Float-or-Slack-So-It-Can-Be-Added-to-a-View Essentially, we have complex projects with...

    Type

    Questions

    Views

    867

    Likes

    0

    Replies

    0
  • I would also like to be able to use it when I copy tasks for repeated use in a project. (E.g., molded parts all have the same steps to design and qualify each tool and part.) Right now, the tasks all have the same names and I can only tell what it refers to by the parent task name. I would prefer to...

    Type

    Ideas

    Views

    439

    Likes

    0

    Replies

    0
Top badges earned by ThereseGr
Customize the badges you want to showcase on your profile