Project Duration Type: Add Ability to Change in Project Details

Avatar

Level 3

5/29/18

Our system uses "Calculated Assignment" as the default duration type for new projects. That setting is appropriate for the proof projects that are managed through Workfront.

However, for non-proofing projects, other duration types may be better. I have found that changing the duration type from Calculated Assignment to Simple of individual tasks, once the project has started, changes the duration of the tasks to 0 days.

I would like the ability in the Project Details, to change the default duration type, so that all new tasks in the project take on the specified duration type.

1 Comment

Avatar

Community Advisor

9/19/18

You should be able to change this by going to Edit Task (you can select all tasks at once) and changing it. I would suggest making a template so you don't have to do it every project