How to Filter out the Resources no longer working on the project

Avatar

Level 3

Hi Community,

How can I filter out resources that are no longer working on project so that I can only see resources who are currently working on the project as shown in screenshot below. 

I have tried bunch of filters on the utilization screen but it doesn't seems that the filter on the utilization tab is working as expected, 

Any help will be appreciated, 

 

meshackOm_0-1708628879160.png

 

 

2 Replies

Avatar

Community Advisor

I made a filter for Assignment / Planned Hours / Greater than 0 -- this seemed to work for me. What sort of errors do you get?

Avatar

Community Advisor

What Skye said…

ScreenShot 2024-02-27 at 12.29.46 PM.jpg

or you could just use greater than 0