So for the actual planning part and getting that info, our company built a custom solution for annual Scopes of Work (SOWs) and staffing plans to compile all the different excel sheets everyone has. So I'm not much help there. However, I did want to say that one business unit did, which I loved, is put a placeholder project (created from a template) in the various portfolios and spread throughout the year so that it matched the Annual SOWs. (i.e. this client wants 1 email in Q1, a website to launch in September, and a Q4 email so they would put in the three projects in that portfolio in Idea status). Now, we still have a request queue for Project Initiation, BUT, there is a question that says, is the project In Scope or Out of Scope. If it is in scope, they know the already have a project. They will still convert that issue to a project as they want the other info on the request to transfer over, but then they will delete the corresponding placeholder project from the portfolio. (If the project is out of scope, they will create the project and know they don't need to delete a placeholder one because it was not in the original SOW). Hope that is helpful. Anthony Imgrund FCB