My team has just noticed that if a task has a finish-to-finish predecessor only, it will show as Ready to Start when the predecessor isn't actually complete (or showing as green). WF support has explained to me that technically finish-to-finish predecessors can start whenever but just have to finish with the indicated predecessor task. I'm just wondering if anyone has a workaround so that finish-to-finish predecessors will stop showing as Ready to Start in dashboards and reports until the predecessor task is actually complete and the current task can start?
I've attached a picture that demonstrates what I am trying to explain!
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
You can add multiple predecessors that better indicate when it's appropriate for your FF successor to start. For example, if task 31 should finish at the same time as task 30, it's true that task 31 can start any time. However, if you don't want it to start before task 30, then give it the same predecessor as task 30, e.g. task 29 in addition to task 30FF
You can add multiple predecessors that better indicate when it's appropriate for your FF successor to start. For example, if task 31 should finish at the same time as task 30, it's true that task 31 can start any time. However, if you don't want it to start before task 30, then give it the same predecessor as task 30, e.g. task 29 in addition to task 30FF
If the relationship is that task A must finish before task B can start then you should be using the fs predecessor and not the ff predecessor.
The following are the Workfront Dependency Types:
Views
Replies
Total Likes
@DyllenC - were you able to solve your issues?
Views
Replies
Total Likes
Yes I was using the answer I marked as Correct Reply!
Thank you!