Expand my Community achievements bar.

SOLVED

Task Not Showing in Task Report

Avatar

Level 2

Hello...I am beating my head against the wall with this issue and I don't understand it.

 

Can anyone tell me why this task:

Screenshot 2024-11-18 at 1.44.54 PM.png

 

Isn't showing on a report with these filters:

Screenshot 2024-11-18 at 1.45.20 PM.png

 

The project is active, that person is assigned to it, and they haven't marked their portion complete. I am at a loss here..I hope I'm missing something stupid simple.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Don't use Task | Assigned To ID (which only applies if the user is the Task Owner or first person assigned). Maybe use Assignment Users | Name instead. 

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

Don't use Task | Assigned To ID (which only applies if the user is the Task Owner or first person assigned). Maybe use Assignment Users | Name instead. 

Avatar

Level 9

Not stupid, just poor legacy field labeling. "Assigned To ID" should really be called "Task Owner ID" because that's what it's actually pulling. It will only ever get a single person in the filter.